Bridge 11 Update

The last passenger train headed by Standard Class 2 78022 and captured by regular contributor, Chris King, has rumbled across the old ‘Bridge 11’ and all eight concrete bridge components are now on site (see previous report) ready for the big lift starting Monday, 16th March.

Although it has been a few weeks since the concrete beams were moved on site from Ingrow, the civil engineers have not been idle.

Work in the last few weeks has included drilling replacement sleepers in Oakworth Yard ready to take track over the new bridge, laying a pathway through Ingrow Tunnel and, recently, building a walkway between the banks of the River Worth.

What happens now?

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.